- The 168k b/d crude unit will be shut for about 12 days to clean its exchangers
- Work on the 50k b/d hydrotreater is expected to last about 8 days
- In about a week, the 39k coker at the West Plant will run out of feedstock from the crude unit and be put on so-called hot standby until the crude unit ...
Citgo Corpus Christi Shutting Sole Crude Unit, Hydrotreater
Jan. 15, 2025, 7:50 PM UTC